Road Work Schedule Update

Due to weather and unforeseen circumstances, the road milling and paving schedule has been adjusted.

October 28–29: The contractor will be paving the currently milled sections on Schock Rd., Trescott St., and Bartlett St.
November 4 (anticipated): Work will continue with milling and paving on Trescott St., The Beach area, Resort Rd, the remaining portion of Garden Street, and Tucker Street.

We appreciate everyone’s patience and understanding as the schedule shifts with the weather. Thank you!